Ease Faith Ltd v Leonis Marine
Management Ltd [2006] 1 Lloyd's Rep. 673
This was a towage dispute. Brookes & Co.
acted for the Claimant, Ease Faith Ltd ("Ease Faith").
By a towage
agreement under the International Ocean Towage Agreement ("the
sub-towcon") Ease Faith
appointed Leonis Marine Management Ltd ("Leonis"),
a tug owner, to tow the dead vessel "Kent Reliant"from
Balboa, Panama, to China for demolition.
Leonis itself entered into
an agreement with the Part 20 Defendant tug owner, Cloudfree
Shipmanagement Ltd ("Cloudfree"). This agreement ("the
head towcon")
was, again, in the International Ocean Towage Agreement form,
but was not identical to the sub-towcon. The sub-towcon contained
the express provision that the tug was to proceed at utmost
dispatch whereas there was no such provision in the head towcon.
The vessel was delayed in reaching China. There were three identifiable
periods of delay: there had been a delay where the tug stopped
steaming because a hire instalment had not been paid; there had
been a subsequent delay when the convoy arrived off Shanghai
when Cloudfree purported to exercise a lien over "Kent Reliant"
and there had been delays caused because the tug had proceeded,
at times, using only one of her two engines. Because of the delay,
the purchasers in China were only prepared to pay a reduced purchase
price because of the late delivery.
Ease Faith claimed damages from Leonis on the grounds that the
tug failed to carry out the voyage with due dispatch. Ease Faith's
claimed for (i) additional pilot and escort charges
arising from the delay, (ii) the reduction in the purchase price
for the "Kent Reliant" and (iii) the loss of interest arising
from the delay in receiving the purchase price.
Leonis defended the claims and brought Part 20 proceedings against
Cloudfree. Cloudfree defended the claim and made a number of
counterclaims. Cloudfree claimed that Leonis had misrepresented
the displacement of the Kent Reliant; she had been described
in the towcon as being in "light ballast condition", whereas
she was heavier than represented. As a result of this, Cloudfree
argued that they had suffered loss because the tug had consumed
extra bunkers.
Both Cloudfree and Leonis submitted that Ease Faith's claims
were excluded by clause 18.3 of the standard wording of the towcon
form which provided that, "Save for [specified provisions] neither
the tug owner nor the hirer shall be liable to the other party
for loss of profit, loss of use, loss of production or any other
indirect or consequential damage for any reason whatsoever".
Cloudfree also argued that Leonis were estopped by convention
from complaining that the delay when the tug stopped steaming
because an instalment of hire had not been paid constituted a
breach of the head towcon.
The Court held that,
1
There were undertakings in both towcons that "Kent Reliant"
was in a light ballast condition and, on the facts, those
undertakings had been complied with. The counterclaims of
Cloudfree and Leonis based on the alleged misrepresentation
failed.
2
The tug had failed to proceed with utmost despatch when
she stopped steaming because a hire instalment had not been
paid.
3
It was implicit in the sub-towcon that the tug would use
both her engines on order to proceed at utmost dispatch.
Leonis were, therefore, in breach of the sub-towcon for failing
to proceed at utmost dispatch during the periods when the
tug only used one of her engines.
4
The term "loss of profit" in clause 18.3 of the towcons
did not refer to the particular venture in which the company
was engaged but to loss of profits generated by future use
of the tug or the tow.
5
Ease Faith's claim against Leonis in respect of pilot
and escort charges and in respect of the reduced price
paid succeeded
6
Although the head towcon did not contain any express provisions
about the speed with which the tug should proceed, it was
an impled term of the head towcon that Cloudfree should have
completed the towing operation with all reasonable dispatch.
7
What was reasonable in the context of a contract providing
for utmost dispatch was not necessarily the same as what
was reasonable in the absence of that stipulation. In this
case, progress at reasonable speed or all reasonable dispatch
was progress at a speed that could reasonably be achieved
if both engines were routinely used. Because the tug had
proceeded at a reduced speed as a result of using only one
of her engines, Cloudfree were in breach of the implied term
of the head towcon that they should complete the towing operation
with all reasonable dispatch.
8
Leonis were not estopped by convention from complaining
that the delay when the tug stopped steaming
because an instalment of hire had not been paid constituted a
breach of the head towcon
9
Cloudfree were, therefore, in breach of the head towcon.
As a result, Leonis were in breach of their obligations to
Ease Faith. Therefore, Ease Faith's claim for damages against
Leonis succeeded and Leonis were entitled to recover against
Cloudfree in respect of their liability to Ease Faith. Cloudfree's
claims failed.
Andromeda Marine SA v O W Bunker & Trading
A/S (The "Mana") [2006] 2 Lloyd's Rep. 319
By a bunker supply contract with American
time charterers, the Defendants, O W Bunker & Trading A/S ("OW
Bunker"), supplied bunkers to the vessel m.v. "Mana", owned by
the Claimants, Andromeda Marine SA ("Andromeda"). The bunker supply
contract contained an exclusive English jurisdiction clause. The
time charterers went into charter 7 bankruptcy before making payment
for the bunkers. OW Bunkers then sought payment from Andromeda
on the basis that it had a maritime lien against the vessel.
Brookes & Co. acted for Andromeda.
Andromeda commenced proceedings against OW Bunker in England
claiming a declaration that Andromeda was not a party to the
bunker supply contract, It relied on article 17 of the Brussels
Convention which provides that parties can agree that the courts
of a particular contracting state are to have exclusive jurisdiction.
Shortly thereafter, OW Bunker arrested the vessel in Portugal
and subsequently commenced in rem proceedings in the Texas District
Court, asserting a maritime lien. OW Bunker
challenged the jurisdiction of the English Court, submitting
that since Andromeda had asserted that it was not a party to
the contract for the sale of bunkers it could not rely on article
17.
Article 17 of the Brussels Convention
If the parties, one or more of whom is
domiciled in a Contracting State, have agreed that a court
or the courts of a Contracting State are to have jurisdiction
to settle any disputes which have arisen or which may arise
in connection with a particular legal relationship, that
court or those courts shall have exclusive jurisdiction.
Such an agreement conferring jurisdiction shall be either
in writing or evidenced in writing or, in international trade
or commerce, in a form which accords with practices in that
trade or commerce of which the parties are or ought to have
been aware. Where such an agreement is concluded by parties,
none of whom is domiciled in a Contracting State, the courts
of other Contracting States shall have no jurisdiction over
their disputes unless the court or courts chosen have declined
jurisdiction.
The court or courts of a Contracting
State on which a trust instrument has conferred jurisdiction
shall have exclusive jurisdiction in any proceedings brought
against a settlor, trustee or beneficiary, if relations between
these persons or their rights or obligations under the trust
are involved.
Agreements or provisions of a trust instrument
conferring jurisdiction shall have no legal force if they
are contrary to the provisions of Articles 12 or 15, or if
the courts whose jurisdiction they purport to exclude have
exclusive jurisdiction by virtue of Article 16.
If an agreement conferring jurisdiction
was concluded for the benefit of only one of the parties,
that party shall retain the right to bring proceedings
in any other court which has jurisdiction by virtue of this
Convention.
Andromeda, however, argued that it article 17 did apply at the
time the English proceedings were brought because at that time
OW Bunker's case had been that Andromeda was a party to the bunker
supply contract which contained the exclusive jurisdiction clause.
Andromeda argued that it had accepted the English jurisdiction
clause as binding upon it in relation to the claims brought by
OW Bunker. Andromeda argued that OW Bunkers' subsequent case,
that Andromeda was not a party to the supply contract, did not
change the arguments under article 17.
The Court held that it did not have jurisdiction to hear Andromeda's
claim because,
1
For article 17 to apply, the agreement as to exclusive
jurisdiction had to be clearly and precisely demonstrated
not just by looking at the words of the contract but all
the circumstances.
2
The question was whether Andromeda had agreed by acceptance
to be bound by the jurisdiction clause. Although it might
be possible for an acceptance to be demonstrated by the issue
of proceedings in the chosen jurisdiction, Andromeda could
not be said to have accepted, let alone accepted clearly
and precisely, the jurisdiction clause when the purpose of
the proceedings was to deny that it was bound by the contract
which contained the clause. Before a jurisdiction clause
could be "accepted" within the meaning of article 17, there
had to have been some kind of offer capable of being accepted.
All that was on offer in the present case was acceptance
of the contract as a whole or nothing. A person was not entitled
to pick and choose which clauses he would and would not accept.
There was no evidence of Andromeda ever having accepted the
jurisdiction clause or the contract in which it was contained
3
In any event, OW Bunker had never actually asserted that
Andromeda was a party to the bunker supply contract. OW Bunker
had relied on a maritime lien.
4
The time when the court had to judge whether jurisdiction
was properly asserted was the time when the challenge to
the jurisdiction was before it.
ST Shipping & Transport Inc v Vyzantio
Shipping Ltd (The"Byzantio") [2004] EWHC 3339 (Comm)
By a charterparty on an amended Shelltime
4 form, Vyzantio Shipping Ltd, ("Vyzantio") chartered their vessel
m.t. "Byzantio" to ST Shipping & Transport Inc. ("ST Shipping").
Vyzantio was a Maltese company whose registered office was no
more than a nameplate at address in Valletta. Its sole director
was a Greek citizen resident in Greece. Its managers were Aegean
Shipping Management S.A. ("Aegean"). Vyzantio also had a contract
with a firm of Maltese lawyers ("CDRA") for the provision of
registered office services.
A dispute had arisen in respect of the vessel's last voyage
under the charter. The vessel had been sub-chartered for this
last voyage and had been delayed because of engine problems.
On 4 September 2002 ST Shipping sent a fax to Aegean requesting
a six-month extension to the existing 12-month limitation period
as their sub-charterers had indicated that a cargo claim might
arise. Aegean agreed to an extension for any cargo claim. On
12 September 2002 ST Shipping issued a claim form which gave
Vyzantio's address in Malta and was marked "Not for service out
of the jurisdiction". On 20 September 2002 ST Shipping's solicitors
notified Aegean by fax that a dispute had arisen under the charter
inasmuch as the sub-charterers had indicated that a cargo claim
would be forthcoming. The fax did not say that a claim form had
been issued.
There was no further correspondence between ST Shipping and
Vyzantio until after August 2004, however, the claim was pursued.
On 11 March 2003 St Shipping obtained permission from the Court
(in a without-notice application) to issue a concurrent claim
form for service out of the jurisdiction and to serve it in Malta.
They also successfully applied to have the validity of the concurrent
claim form to be extended for six months.
On 28 April 2003 ST Shipping issued a concurrent claim form
but it was not lodged with the Foreign Process Department of
the High Court until 27 August 2003 by which time there was insufficient
time to effect service, so a second application was made, without
notice, to extend the time for service for a further six months.
An extension to 12 March 2004 was obtained.
On 13 November 2003 the concurrent claim form was lodged again
with the Foreign Process Department and thus the process of serving
the claim form in Malta in accordance with Maltese law had begun.
Under Maltese law, where a Maltese company has no representatives
resident in Malta, "Curators" are appointed to received service
on the company's behalf. In this instance, notice of the application
by the Attorney General of Malta to appoint Curators was served
on CDRA on 5 February 2004.
On 2 March 2004 ST Shipping applied, without notice, for a third
extension of time for service of the claim form and, on 3 March
2004, were granted a further extension up to 12 September 2004.
Shortly thereafter, two Curators were appointed to receive service
on behalf of Vyzantio in Malta. The proceedings were duly served
upon the Curators between 16 and 20 April 2004. Vyzantio, however,
failed to enter an acknowledgement of service and, default judgment
was entered against it on 16 July 2004.
Around 10 August 2004 CDRA sent Vyzantio copies of
two Maltese court documents which had been translated into English.
This was the first that Vyzantio knew of the proceedings. Vyzantio
applied on 20 August 2004 to have the claim form, service of
the claim form and default judgment set aside.
Vyzantio argued that the whole action should be set aside because,
1
The claim form had already expired by the time the Court
made its orders of 11 March 2003
2
The order which had been made on 11 March 2003 was actually
dated 31 March 2003 and only took effect on that date. Since
the claim form had, by then expired, an extension of its
validity could not be granted because there was no general
power to grant extensions with retrospective effect.
3
Alternatively, the default judgment should be set aside
under CPR 13.3(1)(a) (defendant having some real prospect
of successfully defending the claim) and/or under CPR 13.3(1)(b)
(some other good reason why the judgment should be set aside).
As to r. 13.3(1)(b), Vyzantio argued that the default judgment
should be set aside because ST Shipping had deliberately
served the claim form by stealth in that the method of service
had not brought the claim to its attention and thus Vyzantio
had been caught unawares.
The Court held that,
1
The claim form had not expired by the time it was extended
on 31 March 2003; the character of a claim form was determined
by whether it was intended to be served out of the jurisdiction
and not upon whether permission to serve it out of the jurisdiction
had been granted. A claim form addressed to a defendant resident
abroad was potentially valid for six months under CPR 7.5(3)
even if it was marked "Not for service out of the jurisdiction".
2
The extension granted on 31 March 2003 was granted pursuant
to an application made within time. The Court had power to
grant the extension even though it made the order after the
period of six months had expired. There was no question of
the order being backdated in contravention of CPR 40.7.
3
Therefore, on the facts, the extensions of time for service
of the claim form were justified and accordingly the claim
form would not be struck out on the ground that the without
notice orders should not have been made.
4
The circumstances in which the default judgment was obtained
did provide a good reason why the default judgment should
be set aside. These circumstances were (1) St Shipping's
decision to serve the claim form in Malta without mentioning
it to Aegean and (2) there had been a very considerable interval
of time between the correspondence about the claim in September
2002 and the date of service in April 2004. This lapse of
time had lulled Vyzantio into believing that the claim was
not being pursued. Accordingly, the default judgment would
be set aside under CPR 13.3(1)(b).
5
Although Vyzantio had a case to answer on the merits, the
issue was not so clear that it could be determined summarily.
Accordingly, the default judgment would also be set aside
under CPR 13.3(1)(a) and since Vyzantio had succeede under
both limbs of CPR 13.3, a condition of securing the claim
was not appropriate.
Brookes & Co. acted for Vyzantio in
this dispute.
Welex A.G. v Rosa Maritime Limited (The"Epsilon
Rosa") [2002] EWHC 762 (Comm)
In early 2001 Liberty Steel and Services
GmbH ("Liberty") purchased 5394 tonnes of steel plates from Welex
A.G. ("Welex"). The delivery terms were c.f.r. free out Szcezecin,
INCO Terms 2000, together with Welex's general purchase terms which
stated (inter alia), "Unless otherwise agreed, bills of lading
tendered under CIF and CFR contracts may be issued incorporating
terms of any charter party".
The vessel, m.v. "Epsilon Rosa", owned by Rosa Maritime Limited
("Rosa") and managed by Epsilon Shipmanagement Ltd ("Epsilon"),
was chartered to transport the cargo. The charterers were Red
Sea Heavy Industries LA ("Red
Sea") who fixed the charter through Red Sea's brokers,
Caspi Cargo Lines ("Caspi").
On 19 March 2001 Caspi sent a recap telex which included the
words "ARB IN LONDON ENGLISH LAW TO APPLY". Clause 47 of the
recap telex had been amended by hand to read: "Arbitration if
any to be settled in London in accordance with the Rules of the
LMAA". Epsilon confirmed that the terms of the recap telex were
in order and that "Epsilon Rosa" was fully fixed.
A bill of lading on the Congenbill form expressly "to be used
with Charterparties" was issued for the carriage of the cargo.
The shippers were shown to be Ilyich Iron and Steel Works and
the consignee was named as "Korympic Steel International G.m.b.H.
on behalf of Welex A.G." The bill of lading had been claused
with ship's remarks that the cargo had been stored in the open,
was wet before shipment and exhibited some rust. Clause 1 of
the bill of lading stated: "All the terms, conditions, liberties
and exceptions of the Charter Party including the Law and Arbitration
Clause are herewith incorporated."
On the vessel's arrival at the discharge port the claimant's
surveyors found that the cargo had been damaged. They believed
that the damage was due to wetting by seawater and blamed leaking
hatchcovers.
On May 31 2001, Rosa sold the "Epsilon Rosa" to Alexia Navigation
Ltd ("Alexia"). In July 2001 Welex arrested the vessel in Portugal.
Welex then filed a claim with the District Court of Szczecin
against Rosa and Alexia claiming US$868,564. Alexia attempted
to lift the arrest proceedings but failed.
On 19 September 2001, Rosa commenced arbitration proceedings
in London pursuant to the fixture evidenced by the recap telex.
In these proceedings Welex sought a declaration that no arbitration
agreement had been incorporated into the contract of carriage
and Rosa applied for an anti-suit injunction restraining Welex
from continuing the proceedings in Szczecin or otherwise prosecuting
proceedings against Rosa other than by way of the arbitration.
Rosa submitted that a charterparty had been executed and therefore
the arbitration clause in it had been incorporated into the contract
of carriage evidenced by the bill of lading. In the alternative,
Rosa submitted that in the event a charterparty had not been
executed, the recap telex and the associated documentation was
sufficient to constitute the charterparty for the purpose of
incorporating the arbitration clause.
The Court held,
1
it was common ground that the reference to
a charter party in clause 1 of the bill of lading referred
to a document or documents. It would not refer to an oral
agreement and it was also common ground that it must have
been agreed and reduced to writing when the bill of lading
was issued.
2
while a contract for chartering a ship was
normally embodied in printed form the parties' agreement
could remain in written fax or telex exchanged. A signed
charterparty was unnecessary. The terms of the charterparty
could be readily identified from the contents of the recap
telex and the standard form to which it referred.
3
the transferee of a bill of lading should not be affected
by oral terms but the submission that where the contract
is contained in or evidenced by a recap telex this did not
qualify for the purpose of having been reduced to writing
could not be accepted.
4
on the facts and the evidence Welex had been aware of and
had approved the fixture; the "charter party" referred to
in the bill of lading was the agreement contained in the
recap telex.
5
on the assumption that English law was applicable, the
arbitration clause referred to in the executed charterparty
(alternatively the recap telex) was incorporated into the
bill of lading.
The conclusion that the arbitration clause referred to in the
executed charterparty was incorporated into the bill of lading
was premised on the assimption that English law was applicable
by virtue of art. 8(2) of the Rome Convention as enacted in the
Contracts (Applicable Law) Act, 1990. The question as to whether
Welex was entitled to rely on the laws of Ukraine or Switzerland
and, if not, whether Rosa was entitled to an anti-suit injunction
was to be heard in a subsequent hearing (Welex A.G. v Rosa Maritime
Limited (The"Epsilon Rosa") (No. 2) [2002] EWHC 2035
(Comm) - see below).
Brookes & Co. acted for Rosa.
Welex A.G. v Rosa Maritime Limited (The"Epsilon
Rosa") (No. 2) [2002] EWHC 2035 (Comm)
Article
8
of the Rome Convention
Material validity
1. The existence and validity of a contract, or of any term
of a contract, shall be determined by the law which would govern
it under this Convention if the contract or term were valid.
2. Nevertheless a party may rely upon the law of the country
in which he has his habitual residence to establish that he
did not consent if it appears from the circumstances that it
would not be reasonable to determine the effect of his conduct
in accordance with the law specified in the preceding paragraph.
This was the second of two hearings, the
first of which had concluded that if English law was applicable,
an arbitration clause referred to in an executed charterparty was
incorporated into the bill of lading.
The issues before the Court in this second hearing were (1)
whether the claimant, Welex was entitled to rely on the laws
of the Ukraine or Switzerland to establish that it did not consent
to the incorporation of the arbitration clause by virtue of art.
8(2) of the Rome Convention and, if not, (2) whether the defendant,
Rosa, was entitled to an anti-suit injunction to restrain Welex
from pursuing proceedings otherwise than by arbitration.
If Welex could rely upon the law of its country of residence,
Switzerland, it could establish that it did not consent to the
arbitration clause because (1) under Swiss lay, Welex would be
bound to those terms to which the original shipper had consented
and (2) under Ukraine law, the shippers were not bound by the
arbitration clause.
It was held by the Court that,
1
the burden was upon Welex to displace the
effect of art. 8(1) of the Rome Convention. The shippers
had presented the Congenbill to the master for signature
and it was not suggested that there was anything unreasonable
in holding Welex to the contract of carriage as a whole.
An arbitration clause is common in such contracts and in
due course Welex succeeded to the shippers' rights and obligations.
There was nothing "eccentric" or unjust in the English law
to hold that both shipper and consignee were bound by the
terms of the dispute resolution clause.
2
the transaction was an entirely conventional
one and there was nothing in the circumstances which rendered
it unreasonable to determine the effect of Welex's conduct
by reference to English law.
3
Welex had not shown sufficient strong reasons
to displace Rosa's entitlement to enforce the contractual
bargain that there would be arbitration in London and therefore
an anti-suit injunction would be granted.
Brookes & Co. acted for Rosa.
Welex A.G. v Rosa Maritime Limited (The"Epsilon
Rosa") [2003] EWCA Civ 938
Welex appealed the above decisions. The issues
for determination were whether the English law and London arbitration
terms in the charterparty were incorporated into the bill of lading
and whether Rosa ws entritled to an anti-suit injunction restraining
Welex from proceeding with its claim in Poland.
The Court of Appeal upheld the decisions of the Commercial Court.
Schiffahrtsgesellschaft MS "Merkur Sky" m.b.H & Co.
K.G. v MS Leerort NTH Schiffahrts G.m.b.H & Co. K.G. ("The"Leerort")
[2001] EWCA Civ 1055
On 19 September 1998 the vessel "Zim Piraeus",
having just entered the harbour, collided with the vessel "Leerort"
in the Jaya Container Terminal, Colombo. Leerort had been lying
in a berth and was laden with cargo. Leerort flooded and there
was severe damage to her cargo.
Brookes & Co. represented the cargo interests.
The owners of "Zim Piraeus", Schiffahrtsgesellschaft MS "Merkur
Sky" m.b.H & Co. K.G. admitted liability, accepting that
the vessel had entered the harbour at excessive speed and that
the master had failed to engage manual control immediately before
going astern when he knew that the vessel's forward speed would
prevent an astern start-up in automatic mode and that having engaged
manual control, the master had failed to put the engine immediately
full astern. They applied for an order limiting their liability
for the collision.
It was held by the Admiralty Court that the owners were entitled
to limit their liability. The cargo interests chalenged the
the owners' rights to limit their liability in the Court of Appeal.
The Court of Appeal held that,
1
it was only the personal
act or omission of a shipowner which defeated the right to
limit liability. In order to defeat the right it was necessary
to identify tyhe causative act or omission on the part of
the shipowner, charterer, manager or operator that caused
the loss. It was only conduct committed with intent to cause
such loss or recklessly with knowledge that such loss would
probably result that defeated the right to limit and this
required foresight of the very loss that actually ocurred,
not merely of the type of loss that occurred.
2
when damage resulted from
a collision the shipowner would only lose his right to limit
if it could be proved that he deliberately or recklessly
acted in a way which he knew was likely to result in the
loss of or damage to the property of another in circumstances
where the same consequences would be likely to flow to his
own vessel.
3
the cargo interests
had not demonstrated that the owners had carried out any
act or made any omission with the intention of bringing
their vessel into collision or performed recklessly with
the knowledge that it was likely to produce this result
4
the owners were entitled
to limit their liability
Other reported cases:
Global Container Lines Ltd
v Bonyad Shipping Co. [1999] 1 Lloyds Rep. 287
Lukoil-Kaliningradmorneft
Plc v Tata Ltd and Global Marine Transportation Inc. [1999]
1 Lloyd's Rep. 365
Lukoil-Kaliningradmorneft
Plc v Tata Ltd and Global Marine Transportation Inc. [1999]
2 Lloyd's Rep. 129
Global Container Lines Ltd
v Bonyad Shipping Co. [1998] 1 Lloyd's Rep. 528.